Demolition of a precast concrete section garage/build a new brick garage/utility room.
The demolition of a concrete section garage built on a raft foundation. planning permission approved. Foundations dug to a depth of 1m. Sub-structure brickwork and blockwork now up to dpc. Concrete oversite complete. 22/12/2011
Brickwork to superstructure started 03/01/2012.
New photo showing brickwork constructed upto the
09/01/2012
Scaffolding erected Thursday 12th January 2012.
Roof trusses erected and brickwork Gables completed 23/01/2012