This new-build project in Gerrards Cross began in December 2024 and is progressing on schedule for completion in June 2026. From the outset, it’s showcased our expertise in complex groundwork, coordination, and problem-solving. Despite challenges like uneven terrain and limited access, our team planned meticulously to manage deliveries, excavations, and safety. Early works included diverting Thames Water infrastructure and completing specialist piling and foundations, where we also resolved unexpected water ingress. Since then, we’ve installed ridge beams, structural steel, brickwork, and utility services, with beam-and-block flooring laid across both floors. The next phase includes roof installation, electrics, plumbing, and fitting windows and doors.